Over the past few weeks, the masonry team has been hard at work constructing the new fireplace in the “Hutch” so it matches the existing, well-loved fireplace in the Lodge.
Final roof framing has also been completed, including a custom-built truss that connects the Lodge extension to the existing structure. The truss was carefully handcrafted by our framing team to blend seamlessly with the original building.





Our electricians and plumbers have been busy completing their initial rough-in work, running wiring for outlets and lighting, and installing the plumbing needed to support the Lodge’s new bathrooms.
In addition, our audiovisual and network contractors have been on site preparing for work that will begin next week. The Lodge will feature a new sound system along with upgraded network service and equipment to ensure reliable connectivity for staff and program needs. And yes—you heard that right—improved Wi-Fi is coming to the counselors’ lounge this summer!


Looking ahead, the next phases of construction will include installing mechanical equipment in the Hutch basement, completing roof shingle installation, and insulating the Hutch space. Equipment orders have also begun, with the prep kitchen equipment scheduled to arrive next week.
We look forward to sharing more updates as the project continues to move forward!