February Update #2

The Lodge project continues to gain momentum, and it is exciting to see the building elevations beginning to take shape. Over the past two weeks, the Hardypond Construction team has been hard at work framing the walls and roof of the “Hutch”. This new extension will soon become a space that proudly celebrates Huckins history and, during the summer months, serves as an expanded counselor lounge.

The Hutch will also feature five bathrooms, two dedicated zoom/meeting rooms, and a small prep kitchen — our new candy store location — which will be ready for its first delivery of Moose Tracks before we know it!

We are thrilled to share that the wraparound porch is now fully framed, and roof sheathing has been installed. The traditional Huckins green roof will come next!

Next, our framing crew will shift their focus to the interior walls and window installation. We’re also preparing for the start of the masonry work on the new fireplace in the Hutch, along with the beginning of electrical and plumbing installation.

Thank you for your continued enthusiasm and support as we build a space that honors our past and strengthens our future.

Share the Spirit