The lodge project is entering its final weeks, and momentum continues to build. Recent work has included insulation installation in the hutch, followed by drywall hanging, taping, and mudding. The wraparound porch is taking shape with decking boards installed, and steps leading down to the flagpole are now underway.


Load More
We are finalizing plans with painting and flooring subcontractors—materials are secured, and that work will begin next week. Plumbers and electricians have returned to complete their final installations, including lighting, fans, the well pump, and full utility connections. Finish carpentry is now in progress as well.

Wraparound Porch - Lakeside

Wraparound Porch - Craftshop Side
Load More
We are excited to be heading into the final month of work and look forward to sharing the completed lodge with the community in the coming weeks.